This 4 page paper looks at two case studies supplied by the student, develops a project schedule with the critical path identified and then looks at cost issues. The bibliography cites 4 sources.
Page Count:
4 pages (~225 words per page)
File: TS14_TEcolumbus.rtf
Buy This Term Paper »
 
Unformatted sample text from the term paper:
critical path, the green tasks are not on the critical path and the arrows indicate the potential period in which it can occur (Berkun, 2005) 1 2 3
4 5 6 7 8 9 10 11 12 A 3 Weeks B 6 weeks
C 2 weeks D 5 weeks E
2 weeks F 6 weeks G
4 weeks This gives us Earliest start time Latest start time Earliest finish time Latest finish time Total slack time A 1
1 3 3 0 B 1 3 6 8 2 C 1 5 2 6 4 D 4 4 8 8 0 E 3 7 4 8 4 F 4
7 9 12 3 Question 2 If we use the crush times rather than the normal times this w what we get 1 2 3 4 5 6 7
A 2 weeks B 4 weeks C 1 week D 3 weeks
E 2 weeks F 5 weeks G 2 weeks This then only gives us one week of
slack for task B. Question 3 If we consider a penalty for every week beyond 6 weeks we can compare the costs for eh crashed and then normal timetable
...