This 6 page paper plans a project where tasks have been allocated a time and number of staff but a schedule has not been completed. The paper completes a schedule, identifies the critical path, costs the labour and considers how quality can be maintained. The bibliography cites 2 sources.
Page Count:
5 pages (~225 words per page)
File: TS14_TEprjplan.rtf
Buy This Term Paper »
 
Unformatted sample text from the term paper:
completed, We have a task list and the requirements, as well as an indication of staff needs. The first task is to calculate the time required for the project, and
staffing requirements and costs. For this we need to develop a schedule, which will also show the critical path (Stover, 2003). It is assumed that there is the need to
complete this project as quickly as possible. To identify the time period as well as produce the figures for the staff we can look at the scheduling, broken down
by each day. Here we are looking at project days and not dates 1 2 3 4 5 6 7 8 9 A 4 4
B 3 3 3 3 C 1 D
4 4 4 4 Staff numbers 7 7 3 3 1 4 4 4 4 IT Supervisor 1 1 1 1 1 1 1 1 1 Skilled Analysts 2
2 1 1 0 2 2 2 2 Analysts 5 5 2 2 1 2 2 2 2 10 11 12 13 14 15 16 17 18 D
4 4 E 5 5 5 F 2 G
3 3 3 3 H 6 6 6 Staff numbers 4 4 5 5 5 5 9 9 9
IT Supervisor 1 1 1 1 1 1 1 1 1 Skilled Analysts 2 2 2 2 2 2 3 3 3 Analysts 2 2 3 3 3 3
...